If a property is connected to the City of Cape Town electricity network, the municipality has a formal embedded-generation authorisation process for applicable solar and battery systems. You should verify which category covers your proposed installation.
What to do before installation
Start with the official City application page. Identify whether the property is inside its electricity supply area, confirm the approved inverter and applicable documentation, and ask your installer who handles electrical sign-off and submission.
The City has published guidance acknowledging an exemption from ECSA-registered-person sign-off for some smaller systems under the updated SANS 10142-1:2026 Edition 3.3. That does not mean installations need no approval or other compliance documents. Check the current official procedure.
Retain the inverter and panel specifications, system drawings, electrical compliance documentation, municipal correspondence, commissioning tests, warranties and manuals. These are useful when selling a property, modifying the system or seeking support.
See Cape Town local time, modelled solar output, daytime generation and potential electricity savings. Transparent assumptions and editable system size.